Development Activity Permit and Farmland Conversion Permit in Korea

To construct a building on land or change the form and quality of land in Korea, you need a development activity permit under the National Land Planning and Utilization Act; to use farmland for non-agricultural purposes, you need a farmland conversion permit (or report) under the Farmland Act. A development activity permit can be deemed to include the farmland conversion permit, and a farmland conservation charge is imposed on farmland conversion.

ConsultationGet a Quote

Last updated

Licensing service

Short answer

A development activity permit (개발행위허가) is obtained from the mayor, county head or equivalent by anyone who wants to construct a building or install a structure, change the form and quality of land, extract earth and stone, or subdivide land; if the land is farmland, a farmland conversion permit (농지전용허가) or report is also needed and can be deemed included in the development activity permit. Unless there is a special reason, a decision on a development activity permit is made within 15 days of the application (excluding deliberation and consultation periods), and a farmland conservation charge is imposed on farmland conversion. YouSun Administrative Agency prepares and files the permit application, business plan and damage prevention plan on your behalf.

Who typically engages us

  • Individuals buying farmland or forest land to build a country house or warehouse
  • Corporations preparing a site for a factory or logistics warehouse
  • Farmers building agricultural facilities such as farmer housing or livestock barns
  • Landowners subdividing land to sell or develop it

Development activity and farmland conversion permits at a glance

Who needs it
Constructing buildings or installing structures, changing the form and quality of land, extracting earth and stone, subdividing land, or stockpiling goods for 1 month or more in green, management or natural environment conservation areas / farmland conversion, i.e. using farmland for non-agricultural purposes
Requirements
Development activity scale suited to the zoning (for example, land form and quality changes under 10,000 square metres in residential, commercial, natural green and production green areas); conformity with the urban/county management plan; harmony with the surrounding environment and landscape; a plan to secure infrastructure / for farmland conversion: appropriate purpose and area, no damage to neighbouring farmland, and a suitable business plan and funding plan
Process
Check zoning, land category and deemed permits → prepare the business plan and design documents → submit the permit application → consultation with related agencies and urban planning committee deliberation (where applicable) → pay the farmland conservation charge (for farmland conversion) → permit decision → completion inspection after works
Documents
Development activity permit application; proof of ownership of or right to use the land; project documents and design documents such as the site plan; public facilities statement, drawings and budget breakdown / farmland conversion permit application; business plan; cadastral map and topographic map; damage prevention plan (where applicable)
Timeline
Development activity permit within 15 days (excluding deliberation and consultation periods) / farmland conversion permit decided by the Minister after a 10-day stage at the si/gun/gu and a 10-day stage at the province or metropolitan city; supplement time is separate

Common situations

Pick the question closest to your case: each one gives the conclusion first, then what changes it, the documents involved and the expected timeline.

  1. What permits do I need to buy farmland in Korea and build a country house on it?

    Short answer You need a development activity permit for the construction and the change in land form and quality, and a farmland conversion permit to use the farmland as a housing site. If you submit the farmland conversion documents together with the development activity permit application, the farmland conversion permit can be deemed granted.

    • An individual who is not a farmer builds a house Submit the documents for the deemed farmland conversion permit (business plan, cadastral map, damage prevention plan, etc.) with the development activity permit application, and pay the farmland conservation charge before the permit.
    • A farmer builds farmer housing First check whether a farmland conversion report to the head of the si/gun/gu applies instead of a farmland conversion permit.
    Documents
    Development activity permit application; proof of ownership of or right to use the land; site plan and design documents; farmland conversion business plan; certified cadastral map and topographic map; damage prevention plan (where applicable)
    Timeline
    Development activity permit within 15 days (excluding deliberation and consultation periods) / in practice, farmland conversion consultation and supplement time are added
    Read more
  2. Is there an area limit for a land form and quality change permit to build a logistics warehouse on management area land in Korea?

    Short answer Yes. The scale of land form and quality changes under a development activity permit is set by zoning: under 30,000 square metres in management and agricultural/forestry areas, under 30,000 square metres in industrial areas, and under 5,000 square metres in conservation green and natural environment conservation areas.

    • The planned area is within the scale for the zoning Apply after meeting the remaining permit standards, such as conformity with the urban/county management plan, an infrastructure plan and harmony with the surroundings.
    • The site is farmland Prepare the deemed farmland conversion documents along with the development activity permit and plan for the farmland conservation charge payment.
    Documents
    Development activity permit application; proof of ownership of or right to use the land; project documents such as the site plan; building use and scale documents; public facilities statement, drawings and budget breakdown
    Timeline
    Within 15 days (excluding urban planning committee deliberation and consultation with related agencies)
  3. Can farmland inside an agricultural promotion zone in Korea be converted to another use with a permit?

    Short answer Farmland in an agricultural promotion area passes the conversion permit review only if it does not violate the rules on agricultural promotion areas, so the standard is stricter than for farmland outside such areas. The farmland conservation charge rate is also higher, at 30 percent of the officially assessed individual land price, compared with 20 percent outside promotion areas.

    • The planned use is permitted in the agricultural promotion area Apply for the farmland conversion permit with an appropriate conversion purpose and area and a plan to prevent damage to neighbouring farmland.
    • The planned use is not permitted Meeting the conversion permit review standards would be difficult, so consider a different site.
    Documents
    Farmland conversion permit application; business plan (purpose of conversion, implementation period, site plan, funding plan, etc.); proof of ownership of or right to use the land; cadastral map and topographic map; damage prevention plan
    Timeline
    Decided by the Minister after a 10-day stage at the si/gun/gu and a 10-day stage at the province or metropolitan city / in practice, it depends on any supplements
  4. How long does a development activity permit take in Korea, and does deliberation make it longer?

    Short answer Unless there is a special reason, a development activity permit decision is made within 15 days of the application, but urban planning committee deliberation and consultation with related agencies are not counted in those 15 days. So if deliberation or consultation applies, the actual schedule is longer.

    • No deliberation or consultation is needed and the documents are complete You receive a permit or refusal within 15 days; if farmland conversion is involved, you pay the farmland conservation charge before that.
    • Urban planning committee deliberation or consultation with related agencies is needed The decision comes after supplements based on the deliberation or consultation results, so leave room in the schedule.
    Documents
    Development activity permit application; project documents and design documents; consultation documents with related agencies (where applicable)
    Timeline
    Statutory: within 15 days (excluding deliberation and consultation periods) / in practice, deliberation and supplement time are added
    Read more
  5. What cost items come with a development activity permit in Korea, and is there a separate charge for farmland?

    Short answer The largest statutory cost item is the farmland conservation charge imposed on farmland conversion: the officially assessed individual land price multiplied by 30 percent for promotion area farmland or 20 percent for other farmland, then by the converted area, subject to a cap. A performance deposit may be required as a condition of the development activity permit, but it is a deposit returned after the completion inspection.

    • The land is farmland Pay the farmland conservation charge before the permit, and if needed submit an instalment payment application with it.
    • The permit carries a performance deposit condition Deposit a performance deposit of up to 20 percent of the total construction cost and get it back after the completion inspection.
    • Design or surveying is needed Design documents and surveying are done by specialist firms, so budget those costs separately from the permit.
    Documents
    Development activity permit application; farmland conversion business plan; instalment payment application (where applicable)
    Timeline
    The charge is paid before the permit; the performance deposit is returned after the completion inspection
  6. Do I need a land subdivision permit to split my land into several lots for sale in Korea?

    Short answer Land subdivision is subject to a development activity permit. However, subdividing a building site that has a building on it is excluded from development activity permits.

    • You subdivide land without buildings Apply to the mayor or county head with the development activity permit application and project documents.
    • You subdivide a site with a building on it Check with the competent authority whether another procedure applies instead of a development activity permit.
    Documents
    Development activity permit application; proof of ownership of or right to use the land; project documents
    Timeline
    Within 15 days (excluding deliberation and consultation periods)
  7. I am a farmer. Do I need a farmland conversion permit to build a livestock barn or produce warehouse on my own farmland in Korea?

    Short answer Agricultural and livestock facilities (with some exceptions) and facilities for distributing and processing agricultural and fishery products are subject to a farmland conversion report to the head of the si/gun/gu, not a farmland conversion permit. Whether a development activity permit is needed for the construction itself is assessed separately.

    • The facility is one subject to a report Submit the farmland conversion report to the head of the si/gun/gu, and if construction or a land form change is involved, also prepare a development activity permit.
    • The facility is excluded from the report scheme Proceed through the farmland conversion permit procedure.
    Documents
    Farmland conversion report and the attachments required by the competent authority (business plan, proof of ownership of or right to use the land, cadastral map, etc.)
    Timeline
    Depends on the competent authority's review and any supplements
  8. I changed the form and quality of land in Korea without a permit. What should I do now?

    Short answer Changing land form and quality without a development activity permit can lead to imprisonment of up to 3 years or a fine of up to KRW 30 million, and if farmland was converted without a permit, penalties under the Farmland Act (농지법) may also apply separately. First confirm what measures the competent authority is taking, then respond.

    • Farmland outside a promotion area was converted without a permit This can lead to imprisonment of up to 3 years or a fine of up to 50 percent of the land value, so decide how to proceed following the competent authority's guidance.
    • Farmland in an agricultural promotion area was converted without a permit This can lead to imprisonment of up to 5 years or a fine of up to the land value.
    Documents
    Notice from the competent authority; land registry and cadastral records; photos of the current state
    Timeline
    Depends on the competent authority's enforcement schedule
  9. We applied for a development activity permit in Korea and got a supplement request over damage to nearby farmland and landscape issues.

    Short answer Harmony with the surrounding environment and landscape and prevention of damage to neighbouring farmland are items in both the development activity permit standards and the farmland conversion review standards, so failing to submit plans that answer the supplement request becomes grounds for refusal.

    • Damage to farming or living conditions on neighbouring farmland was raised Revise the damage prevention plan to show that the measures to prevent damage are sound.
    • Landscape, planting, or hazard and pollution prevention was raised Revise the relevant design documents and budget breakdown, and reflect in advance any items likely to be attached as permit conditions.
    Documents
    Supplement request; damage prevention plan; landscape, planting and hazard prevention design documents with budget breakdown
    Timeline
    Supplement time is excluded from the statutory processing period, and the review resumes after the supplement is submitted
  10. What documents does a land form and quality change permit in Korea require, and can they be submitted online?

    Short answer You attach to the development activity permit application proof of ownership of or right to use the land, project documents such as the site plan, a public facilities statement with drawings and budget breakdown, and design documents with budget breakdowns for hazard prevention, pollution prevention, landscape and planting; the application can be submitted through the Korea Land Use Information System (국토이용정보체계).

    • You change the form and quality of land you are leasing Prepare proof of the right to use the land instead of ownership.
    • Farmland is included Also submit the business plan, cadastral map and damage prevention plan for the deemed farmland conversion permit.
    Documents
    Development activity permit application; proof of ownership of or right to use the land; project documents such as the site plan; public facilities statement, drawings and budget breakdown; hazard prevention, landscape and planting design documents with budget breakdown
    Timeline
    Within 15 days (excluding deliberation and consultation periods)
    Read more
  11. If I hire an administrative agent for a development activity permit in Korea, what will they handle?

    Short answer YouSun Administrative Agency reviews zoning and deemed permit relationships, prepares the development activity permit application, farmland conversion business plan and damage prevention plan, and handles filing with the competent authority and supplement responses. Surveying, design and civil engineering documents, environmental impact assessment reports and property appraisals belong to specialist bodies and licensed professionals, so we do not handle them.

    • You are reviewing land before buying it We first set out the zoning, land category, agricultural promotion area status and which permits are needed.
    • Design documents are ready We prepare and file the application and deemed permit documents based on the design documents.
    Documents
    Land registry and cadastral records; land use plan information; design documents (prepared by a design office); project outline
    Timeline
    Within 15 days (excluding deliberation and consultation periods) / in practice, design, consultation and supplement time are added
    Read more

Summary

  • Development activity permit: construction, installing structures, changing the form and quality of land, quarrying, land subdivision, etc.; granted by the Mayor of the Special or Metropolitan City or the city mayor or county head; processing period of 15 days on the application form.
  • Farmland conversion permit: apply to the head of the si/gun/gu where the farmland is located (after review, forwarded via the si/do governor to the Minister for the permit); some uses, such as farmers' houses, need only a conversion report.
  • Statutory costs: the farmland conservation charge (30% or 20% of the individual officially assessed land price per ㎡, capped at KRW 50,000 per ㎡); confirm development activity permit application fees with the competent authority.
  • Common: carrying out development activity or farmland conversion without a permit is a criminal offense.

How do a development activity permit and a farmland conversion permit differ, and do I need both?

A development activity permit is required from the Mayor of the Special City, Metropolitan City or Special Self-Governing City, the Governor of the Special Self-Governing Province, or the city mayor or county head for anyone who intends to construct a building or install a structure, change the form and quality of land, quarry earth and stone, subdivide land (other than a lot with a building on it), or pile goods for 1 month or more in a green area, management area or natural environment conservation area. A farmland conversion permit is required under the Farmland Act for anyone who intends to convert farmland. When a development activity permit is granted, the farmland conversion permit or consultation and the farmland conversion report under the Farmland Act can be deemed granted, so first check whether the land is farmland and whether the deemed-permit rule applies. Activities under urban/gun planning projects, emergency measures for disaster recovery, and the rebuilding, extension or reconstruction of buildings that need only a report under the Building Act, among others, are excluded from the permit requirement.

What are the requirements for a development activity permit and a farmland conversion permit?

(1) Development activity permit standards: the activity must suit the scale of development permitted for the zoning district, must not conflict with the urban/gun management plan and growth management plan, must not hinder urban/gun planning projects, must harmonize with the surrounding environment and landscape, and must have an appropriate plan for installing infrastructure and securing land for it. Scale examples: for changes to the form and quality of land, less than 10,000 square meters in urban residential, commercial, natural green and production green areas; less than 30,000 square meters in industrial areas; less than 30,000 square meters in management and agricultural/forest areas; and less than 5,000 square meters in conservation green areas and natural environment conservation areas.

(2) Farmland conversion review standards: for farmland in an agricultural promotion area, no violation of the relevant rules; the land can be used appropriately for the purpose of conversion; the converted area is appropriate; there is little need to keep preserving the farmland; there is no damage to farming or living conditions on neighboring farmland (if damage is expected, the prevention plan is sound); and the business plan and funding plan are appropriate.

(3) Conditions and performance guarantees: a development activity permit may carry conditions on installing infrastructure, preventing hazards and environmental pollution, landscaping and the like, and a performance deposit (up to 20% of the total construction cost) may be required.

Which documents are needed for a development activity permit and a farmland conversion permit?

For a development activity permit, attach to the development activity permit application: proof of ownership or use rights over the land; project drawings such as a site plan (for changes to the form and quality of land and quarrying); design documents (for installing structures); documents stating the use and scale of the building; a schedule, drawings and cost breakdown for public facilities; and design documents and cost breakdowns for hazard prevention, pollution prevention, landscaping and the like. Documents for consultation with other administrative agencies may also be needed. The application and documents can be submitted through the National Land Use Information System. For a farmland conversion permit, attach to the farmland conversion permit application: a business plan stating the purpose of conversion, the project operator, the project period, the facility layout, the funding plan and the facility management and operation plan; proof of ownership or use rights over the land; a certified copy of the cadastral or forest map and a topographic map showing the planned conversion area; and, where applicable, a plan to prevent damage to neighboring farmland. If you apply to pay the charge in installments, add an installment payment application.

What is the procedure for a development activity permit and a farmland conversion permit?

(1) Check the zoning district, land category, whether the land is in an agricultural promotion area, and the deemed-permit relationship → (2) prepare the business plan and design documents (design and surveying by specialist firms) → (3) submit the development activity permit application (and documents for any deemed permits) → (4) go through consultation with other administrative agencies and urban planning committee review where needed → (5) for farmland conversion, pay the farmland conservation charge in advance, before the permit is granted → (6) decision to grant or refuse the permit (notified in writing or through the National Land Use Information System) → (7) completion inspection after construction. A farmland conversion permit goes through a stage in which the head of the si/gun/gu reviews the application and submits it via the si/do governor to the Minister of Agriculture, Food and Rural Affairs.

How long do a development activity permit and a farmland conversion permit take?

Unless there are special reasons, a development activity permit must be granted or refused within 15 days of the application (excluding the period for urban planning committee review or consultation with other administrative agencies), and the processing period on the application form is also 15 days. For a farmland conversion permit, the head of the si/gun/gu sends the application to the si/do governor within 10 days of receiving it, and the si/do governor then submits it to the Minister within 10 days; the application form shows the processing period for each stage. Time for consultation, review and supplementation is separate.

Which authority receives a development activity permit and a farmland conversion permit?

A development activity permit is applied for to the Mayor of the Special City, Metropolitan City or Special Self-Governing City, the Governor of the Special Self-Governing Province, or the city mayor or county head; a farmland conversion permit is applied for to the head of the si/gun/gu with jurisdiction over the farmland (the permitting authority is the Minister of Agriculture, Food and Rural Affairs). Uses subject to a farmland conversion report, such as farmers' houses and agricultural and livestock facilities, are reported to the head of the si/gun/gu.

What are the statutory costs for a development activity permit and a farmland conversion permit?

A farmland conservation charge is imposed on farmland conversion. The charge per square meter is the most recently published individual officially assessed land price as of the imposition date, multiplied by 30% for farmland in an agricultural promotion area or 20% for farmland outside it, with a cap of KRW 50,000 per square meter. Confirm application fees for the development activity permit and the farmland conversion permit with the competent authority. The performance deposit is not a cost but a deposit returned after the completion inspection.

Why is a development activity permit or a farmland conversion permit refused?

Typical reasons are failing the development activity permit standards (exceeding the scale, conflicting with the urban/gun management plan, not harmonizing with the surroundings, an inadequate infrastructure plan, etc.), failing the farmland conversion review standards (an unsuitable conversion purpose, damage to neighboring farmland, an inadequate business or funding plan, etc.), and not responding to requests to supplement deficient documents. Carrying out development activity without a permit can lead to imprisonment of up to 3 years or a fine of up to KRW 30 million; converting farmland outside an agricultural promotion area without a permit can lead to imprisonment of up to 3 years or a fine of up to 50% of the land value (for farmland in an agricultural promotion area, imprisonment of up to 5 years or a fine of up to the land value).

What can an administrative agent help with?

YouSun Administrative Agency prepares documents such as the permit application, business plan and damage prevention plan, reviews the requirements, and submits them to the authority on your authorization. Land surveying, preparing design documents, architectural and civil engineering design, preparing environmental impact assessments, and appraisal belong to specialist organizations and licensed professionals and are not handled. Work restricted by other laws cannot be handled, and litigation or court representation is outside the scope of an administrative agent and is not offered. Whether a permit is granted is decided by the competent authority.

FAQ

Frequently Asked Questions

Q. When is a development activity permit needed?

A. When you intend to carry out development activities set by Presidential Decree, such as constructing a building or installing a structure, changing the form and quality of land, quarrying earth and stone, subdividing land, or piling goods for 1 month or more in a green area, management area or natural environment conservation area.

Q. How long is the processing period for a development activity permit?

A. Within 15 days unless there are special reasons, excluding the period for urban planning committee review or consultation with other administrative agencies.

Q. If I get a development activity permit, do I need a separate farmland conversion permit?

A. When a development activity permit is granted, the farmland conversion permit or consultation and the conversion report can be deemed granted. To benefit from this, submit the related documents required by the relevant law together with the development activity permit application.

Q. How is the farmland conservation charge calculated?

A. Multiply the individual officially assessed land price by 30% for farmland in an agricultural promotion area or 20% for other farmland to get the amount per square meter, then multiply by the converted area; the cap is KRW 50,000 per square meter.

Q. Are there cases where a farmland conversion report is enough?

A. Farmers' and fishers' houses, agricultural and livestock facilities (with some exceptions), facilities for distributing and processing agricultural and fishery products, communal convenience facilities for farmers such as village halls, and agricultural and fishery research facilities, fish farms and aquaculture farms are reported to the head of the si/gun/gu as a farmland conversion report.

Q. When is the performance deposit returned?

A. It is returned immediately when the permit holder passes the completion inspection.

Q. What if I change the plan after obtaining the permit?

A. To change matters approved under a development activity permit, you need a change permit; for minor matters such as shortening the project period, notify the authority without delay after the change. Changes to key matters of a farmland conversion permit, such as the area or boundaries, also require a change permit.

Key terms

Development activity and farmland conversion permits: key terms explained

Development activity permit (개발행위허가)
A permit obtained from the Mayor of a Special or Metropolitan City, the Mayor of a Special Self-Governing City, the Governor of a Special Self-Governing Province, or a city mayor or county head by anyone who wants to construct buildings or install structures, change land form and quality, extract earth and stone, or subdivide land.
Change of land form and quality (토지의 형질 변경)
An act that changes the form and quality of land; it is subject to a development activity permit, and the permitted scale is set by zoning.
Farmland conversion permit (농지전용허가)
A permit obtained through the head of the si/gun/gu where the farmland is located by anyone who wants to use farmland for purposes other than agriculture, such as crop cultivation; the permitting authority is the Minister of Agriculture, Food and Rural Affairs (농림축산식품부장관).
Farmland conversion report (농지전용신고)
A report filed with the head of the si/gun/gu when converting farmland for specified facilities such as farmer housing, agricultural and livestock facilities, and facilities for distributing and processing agricultural and fishery products.
Deemed permits (인허가 의제)
A scheme under which obtaining a development activity permit is treated as obtaining the farmland conversion permit, consultation or report whose documents were submitted with it.
Farmland conservation charge (농지보전부담금)
A charge imposed on farmland conversion, based on a per-square-metre amount equal to the officially assessed individual land price multiplied by 30 percent for promotion area farmland or 20 percent for other farmland.
Performance deposit (이행보증금)
Money deposited, up to 20 percent of the total construction cost, to secure performance of development activity permit conditions, and returned after the completion inspection.
Completion inspection (준공검사)
The procedure for confirming, after works under a development activity permit are finished, that they were carried out as permitted.

Our office

YouSun Administrative Agency

YouSun Administrative Agency is a licensed administrative agent office (행정사사무소) on Toegye-ro in Jung-gu, Seoul. We prepare and file permit, registration and report applications with Korean government agencies on behalf of clients, in Korean, English, Chinese and Japanese.

Address
3F Seongwoo Bldg, 324 Toegye-ro, Jung-gu, Seoul 04614, Korea
Hours
Mon–Fri 09:30–17:30 (KST), closed weekends and public holidays
Languages
Korean · English · Chinese · Japanese

Related Pages

Contact

YouSun Administrative Agency (+82-2-325-8222) supports document review and filing with the competent authority.